IB Business Management 5.6 · HL only

Production planning (HL only)

Has the business got the right materials, in the right place, at the right time, and is it using its people and machines well enough to cover the cost of having them?

What you will learn

  • HL Understand how local and global supply chains work and how just-in-time differs from just-in-case
  • HL Know how a stock control chart shows lead time, buffer stock, reorder level and reorder quantity
  • HL Know how to measure capacity utilization, defect rate, productivity and operating leverage, and what each shows
  • HL Understand how to compare the cost to buy with the cost to make, alongside non-cost factors

You must be able to

  1. HL Calculate capacity utilization rate, defect rate, labour and capital productivity and productivity rate
  2. HL Calculate reorder level and maximum stock, and construct a labelled stock control chart
  3. HL Calculate the cost to buy and cost to make, and evaluate whether to make or buy
  4. HL Evaluate whether a business should use just-in-time or just-in-case for a given input
  5. HL Calculate operating leverage and the effect of a change in output on profit
  6. HL Explain one advantage and one disadvantage of a global supply chain over a local one

1The local and global supply chain process (AO2)

A supply chain = the whole sequence of businesses and activities that turns raw materials into a finished product in a customer's hands. The supply chain process = how those steps are planned and run.

Stages to name: sourcing materials and components, making, storing, transporting and delivering (including taking returns). Information and money flow back as orders and payments.

A chain is local when most steps happen close to the point of use, often in one region or country. It is global when suppliers, factories or customers are spread across several countries.

Local supply chainGlobal supply chain
Costoften higher input prices; lower transport and import costsoften lower input prices or wages; higher transport, tariffs and exchange-rate exposure
Lead timeshort and predictablelong, exposed to port delays, customs and weather
Control and qualityeasy to visit and inspect suppliersharder to monitor; other standards and languages
Ethics and sustainabilityeasier to check working conditions and cut transport milesharder to check labour practices; longer journeys use more fuel
Fit with JITgood: short lead times and frequent deliveriespoor unless stocks are held nearby

Managing the chain is a set of choices:

  • Which stages to own. Taking over a supplier, distributor or shop is vertical integration. It buys control over timing, quality and cost, but ties up money and management time outside the core.
  • Which suppliers, and on what terms. Delivery dates, penalties for lateness, and standards on pay, safety and materials, often in a code of conduct.
  • How closely to check, and who buys. One central purchasing team, or each site choosing its own.

Technology shifts these choices. Online selling reaches buyers with no wholesaler or shop between. Shared tracking data shows where a shipment is, though not how it was made.

How to use it

  • Neither local nor global is automatically better. Local suits fresh goods or a changing range. Global can suit a scarce material or a low price, if the business can afford the larger stock a long lead time needs.
  • A poorly run chain costs more than its invoices show. Late deliveries stop work, faulty inputs reach the line, response to new demand is slow, and the brand is blamed for a scandal at a supplier.
  • Tie it to the case: what is the item, how long does it take, what does a late delivery cost?

2Just-in-time and just-in-case (AO3)

JIT (5.3): materials arrive close to when needed and goods are made to match demand, so stock stays very low.

Just-in-case (JIC) = the opposite habit: holding a cushion of stock in case demand jumps or a delivery is late.

The guide puts the difference between the two at AO3: compare them and judge which suits a business.

Stock costs money, and so does running short. JIT and JIC trade one against the other.

Holding too much (stockpiling)Holding too little (stock-out)
storage space, insurance, securityproduction stops while staff and machines wait
cash tied up that could earn a return elsewhereorders are late or lost; customers leave
goods that spoil, are damaged, or go out of fashionrush orders at higher prices; overtime to catch up
JITJIC
Stock heldminimalsubstantial, including buffer stock
Cost of holding stocklow: little space, cash or damagehigh: storage, insurance, tied-up money, risk of going out of date
Protection against a late deliveryalmost nonegood: the buffer covers it
Needs from suppliersvery reliable, close, quick to deliver; frequent small orders mean more adminlittle: can tolerate slower or distant suppliers
Response to a sudden rise in demandweak unless suppliers can flexstrong while stock lasts
Risk if demand fallslow: little stock to be left withhigh: stock may be unsold or obsolete

What decides it: supplier reliability and distance, the cost of a stoppage against holding stock, whether the item is perishable, bulky or valuable, and how steady demand is. Many firms use both: JIT for cheap, easily replaced items; JIC for scarce or critical ones.

Worked comparison. Brindle Joinery (an invented firm) fits cupboards and keeps a buffer of 2,000 hinges, each costing $0.40.

The stock ties up 2,000 × 0.40 = $800. At a holding cost of 15 percent of value a year, that is $120. A day with no hinges stops the fitters and loses $1,900 of contribution.

If the supplier is late even once a year, the buffer earns back over fifteen times its cost. So JIC is cheaper here, although it looks wasteful on the shelf.

Reverse the figures (expensive stock, a supplier next door that has never been late) and JIT wins. Stock is insurance as well as a cost.

3Stock control charts (AO2, AO4)

A stock control chart = one stock item's level plotted against time. It shows when to reorder, how much to order and how close stock comes to running out. The guide names four features.

  • Lead time: how long a supplier takes to deliver, counted from the day the order goes in.
  • Buffer stock: a safety cushion for a late delivery or a jump in usage. Stock should fall to it, not into it.
  • Reorder level: the stock figure that triggers the next order.
  • Reorder quantity: the size of each order, in units.

Two more terms: the usage rate (how fast stock falls) and the maximum stock level (the most the business will hold, often set by storage space).

What sets the buffer. Bigger: fast usage, a long or uncertain lead time, an unreliable supplier, costly shortages. Smaller: perishable, fragile or bulky goods, or little storage.

The reorder quantity depends on bulk discounts, storage space and cost, usage, and the cost of placing each order. Frequent small orders keep average stock low; rare large ones raise it.

Running example. Alderby Cycles (an invented business) assembles electric bikes and uses 30 battery packs a day. The supplier delivers 6 days after an order. The owner wants a buffer of 90 packs (3 days' use) and orders 480 packs at a time. The racks hold 600.

Reorder level = buffer stock + (usage rate × lead time)
Reorder level = 90 + (30 × 6) = 270 packs

While the order is on its way, 30 packs a day for 6 days (180 packs) are used. So it reorders when 180 packs plus the buffer remain, and the delivery arrives as stock touches the buffer.

Maximum stock level = buffer stock + reorder quantity
Maximum stock level = 90 + 480 = 570 packs

The racks hold 600, so the plan fits. The pattern repeats:

Days from delivery to reorder = 570 − 270 ÷ 30 = 10 days
Days between orders = reorder quantity ÷ usage rate = 480 ÷ 30 = 16 days
Figure 1 · Stock control chart for battery packs at Alderby Cycles Stock of battery packs (units) Time (days) maximum 570 reorder level 270 buffer stock 90 0 5 10 15 20 25 30 0 90 270 570 lead time 6 days reorder quantity 480 order placed delivery Usage is 30 packs a day. An order for 480 is placed at 270 packs and arrives 6 days later, as stock reaches the buffer of 90.
Figure 1 · Stock control chart for Alderby Cycles

Reading the chart

  • Stock starts at 570 and falls in a straight line (constant usage). At day 10 it hits 270 and an order is placed. It keeps falling through the 6-day lead time.
  • At day 16 it reaches the buffer, 90, and the delivery lifts it to 570. The sawtooth repeats every 16 days.
  • Reading values: lead time is the horizontal gap from order mark to jump. Reorder quantity is the height of the jump. Usage rate is the fall in stock divided by the days taken.

How to construct one:

  1. Time along the bottom, stock in units up the side, both labelled with scales.
  2. Horizontal lines for the maximum level, reorder level and buffer stock.
  3. A line falling from the maximum at the usage rate.
  4. At the reorder level mark the order, and run the line on for one lead time.
  5. At the end of the lead time the line jumps up by the reorder quantity.
  6. Repeat once more.

Working backwards. Sennet Roasters (invented) uses 12 kg of green coffee a day, waits 5 days for a delivery and reorders at 96 kg.

  • Rearranging: buffer = reorder level − (usage × lead time) = 96 − (12 × 5) = 36 kg, three days' use.
  • If it orders 144 kg at a time, the maximum is 36 + 144 = 180 kg.
  • An order goes in every 144 ÷ 12 = 12 days.

What happens when things change.

  • A longer lead time raises the reorder level. At 9 days: 90 + (30 × 9) = 360 packs. The business must order earlier.
  • A higher usage rate also raises it. At 40 a day, 6 days' lead time and a 3-day buffer (120 packs): 120 + (40 × 6) = 360 packs.
  • A late delivery uses the buffer. In Figure 2 the day-16 delivery is 2 days late. Stock falls to 90 − (2 × 30) = 30 packs before 480 arrive. A 3-day delay uses the whole buffer. Anything longer stops assembly.
Figure 2 · A late delivery eats into the buffer stock Stock of battery packs (units) Time (days) maximum 570 reorder level 270 buffer stock 90 0 5 10 15 20 25 30 0 90 270 570 planned delivery, day 16 actual delivery, day 18 30 packs left The delivery due on day 16 is 2 days late, so stock falls to 30 packs, inside the buffer, before 480 more arrive.
Figure 2 · A late delivery eats into the buffer stock

Why stock problems happen: a late supplier, usage above plan, or a forgotten order (automatic ordering at the reorder level removes that risk).

What the chart assumes: steady usage and a fixed lead time. Real life varies, which is why the buffer exists. A bigger reorder quantity means fewer orders but more stock. The chart shows the consequences of the quantity picked, not the best one.

4Capacity utilization rate (AO2, AO4)

Capacity utilization rate = how much of what a business could produce it actually does. The formula is on the formulae sheet:

Capacity utilization rate = actual output ÷ productive capacity × 100

Running example. Tessel Bottles (invented) presses steel water bottles. It can make 8,000 a month and made 6,200.

Capacity utilization rate = 6,200 ÷ 8,000 × 100 = 77.5%

The 22.5 percent left over is spare capacity (under-utilization). Demand above capacity is a capacity shortage.

Working backwards. Turn the formula round. A bakery with capacity of 5,000 loaves at 70 percent makes 5,000 × 0.70 = 3,500 loaves. A plant making 2,400 units at 60 percent has capacity of 2,400 ÷ 0.60 = 4,000 units.

Why it matters

  • Many costs do not fall when output falls: rent, equipment, salaried staff. Tessel's fixed costs are $14,000 a month, and its variable cost is $2.50 a bottle.
OutputCapacity utilizationFixed cost per bottleAverage total cost per bottle
6,20077.5%14,000 ÷ 6,200 = $2.2614,000 + 2.50 × 6,200 ÷ 6,200 = $4.76
8,000100%14,000 ÷ 8,000 = $1.7514,000 + 2.50 × 8,000 ÷ 8,000 = $4.25
  • Using the same equipment more spreads the fixed bill and lowers each unit's cost. At a $7 price the extra 1,800 bottles are very profitable.
  • Low utilization hurts most where fixed costs are high and each extra customer costs little, as in a half-empty hotel, ferry or concert hall.

Why full is not always best

  • Near 100 percent leaves no time to service machines or absorb a rush order. It wears out staff (2.4) and, in services, means queues and rushed customers.
  • No single figure is correct. A launch may run well below capacity, and a firm with small fixed costs can cope with lower use.

If it is too low: find more demand (promotion, new markets, quiet-time discounts), take contract work from other firms, or cut capacity. Rationalization = shrinking the operation by selling or closing what is unused. It saves running costs but possibly jobs.

If it is too high: invest in capacity, raise the price, or keep a waiting list if the rush looks temporary. Or hand part of the output to another firm under contract (subcontracting). It is quicker, but quality and timing are no longer fully in the business's hands.

5Defect rate (AO2, AO4)

A defect = a faulty unit, one that falls short of the specification it was made to. The defect rate = faulty units as a percentage of everything made.

Defect rate = number of defective units ÷ total units produced × 100

Of Tessel's 6,200 bottles, 155 are faulty:

Defect rate = 155 ÷ 6,200 × 100 = 2.5%

Each scrapped bottle wastes at least its variable cost: 155 × $2.50 = $387.50 this month. Add lost sales, re-inspection time, and recalls and lost trust if a faulty one reaches a customer.

If the defect rate falls to 1.5 percent, 93 units are defective, 62 fewer. That saves 62 × $2.50 = $155 a month on materials and labour alone. Backwards: a 4 percent rate on 2,500 units means 100 faulty units.

Reading it

  • A falling rate suggests better quality assurance, training or maintenance (5.3). A rising one may mean worn machines, rushed work (check capacity utilization) or a new supplier's materials.
  • Compare it with the business's own target and past months. No rate is universally acceptable: 2.5 percent is a disaster for aircraft parts and ordinary for some handmade goods.

6Productivity and operating leverage (AO2, AO4)

Productivity = output compared with the inputs used to make it. The guide lists three productivity measures, with operating leverage beside them. Only the productivity rate is on the formulae sheet.

Labour productivity = how much each worker, or each hour of work, turns out.

Labour productivity = total output ÷ number of workers (or hours worked)

Tessel has 20 production workers: 6,200 ÷ 20 = 310 bottles per worker per month. A rise to 6,820 with the same workers gives 341, up 10 percent. Backwards: at 12 units per worker, 45 workers make 540 units.

Capital productivity = output per unit of capital input: machinery, equipment or the money tied up in them.

Capital productivity = total output ÷ capital input

Tessel's two presses run 400 machine-hours in total, so 6,200 ÷ 400 = 15.5 bottles per machine-hour. The measure of capital input depends on the case (hours of use, number of machines, money invested), so state the unit. A low value shows machines idle or breaking down.

Productivity rate is on the sheet:

Productivity rate = total output ÷ total input × 100

Output and input must be in the same terms. For mixed inputs (labour, materials, power), put both in money.

At the $7 selling price (counting every bottle made), Tessel's output is worth 6,200 × $7 = $43,400. Its input cost is 14,000 + (2.50 × 6,200) = $29,500.

Productivity rate = 43,400 ÷ 29,500 × 100 = 147.1%

A rate above 100 means what comes out is worth more than what goes in. Over time, a higher rate means each dollar of input yields more.

To raise it: training, better machines, less waste, motivation (2.4).

Beware: pushing staff harder can raise defects and turnover. Long hours under constant pressure raise an ethical question about their health. Swapping workers for machines raises labour productivity but may lower capital productivity.

Operating leverage = how much a firm's profit swings when sales change, because of its fixed costs.

  • High: high fixed and low variable costs (a rail operator, a ski resort, a capital-intensive plant). Each extra sale adds almost its whole price to profit, but a fall in sales cuts profit sharply. Risk is high.
  • Low: mostly variable costs and labour-intensive (a courier firm paying riders per delivery). Profit is steadier.

The guide prints no formula. Textbooks measure the degree of operating leverage as:

Operating leverage = total contribution ÷ profit at that output
where total contribution = (price − variable cost per unit) × output

Tessel: contribution per bottle is 7 − 2.50 = $4.50. At 6,200, total contribution is $27,900 and profit is 27,900 − 14,000 = $13,900.

Operating leverage = 27,900 ÷ 13,900 = 2.01

Meaning: each 1 percent change in output changes profit by about 2.01 percent.

Check: output up 10 percent to 6,820 gives contribution of 30,690 and profit of $16,690, up 20.1 percent. A 10 percent fall cuts profit by the same 20.1 percent. The higher the figure, the more profit depends on volume.

Caution: the books also describe it in words as fixed costs against variable or total costs. One sets practice as fixed costs ÷ total costs × 100 (fixed costs of $18,000 in total costs of $45,000 give 40 percent). If a question gives its own formula, use it and say so.

7Cost to buy and cost to make (AO3, AO4)

Make-or-buy = deciding whether to make a part or buy it from a supplier. The guide names the two sides: cost to buy (CTB) and cost to make (CTM).

CTB = price per unit × quantity
CTM = (variable cost per unit × quantity) + fixed costs of making it

The fixed costs in CTM are the extra fixed costs making would add (a machine lease, a worker's salary, a new area of floor). Do not add overheads the business pays anyway: they do not change with the decision.

If the question lists several variable items (materials, labour, variable overhead), add them into one cost per unit first.

Running example. Ashgrove Bakery (invented) buys cake boxes at $0.62 each and uses 24,000 a year. It could make them with a machine leased for $4,200 a year, at a variable cost of $0.41 each.

CTB = 0.62 × 24,000 = $14,880
CTM = (0.41 × 24,000) + 4,200 = 9,840 + 4,200 = $14,040

Making saves $840 a year, 5.6 percent of the buy cost. The quantity where the two costs are equal is found as in break-even:

Equal-cost quantity = extra fixed cost ÷ price − variable cost to make = 4,200 ÷ 0.62 − 0.41 = 20,000 boxes
Quantity a yearCTBCTMCheaper
15,0009,30010,350buy
20,00012,40012,400equal
24,00014,88014,040make

Above 20,000 boxes making is cheaper. Below, buying is.

When demand is uncertain, a decision tree (a toolkit tool) puts a probability on each demand level and compares the expected costs. Say Ashgrove's demand is 24,000 boxes (probability 0.6) or 15,000 (0.4).

  • Expected CTB = (0.6 × 14,880) + (0.4 × 9,300) = $12,648.
  • Expected CTM = (0.6 × 14,040) + (0.4 × 10,350) = $12,564.

Making still wins, but by only $84. A small shift in the odds reverses it.

The AO3 step: costs are not the whole decision. A strong answer weighs the numbers against:

For makingFor buying
control of quality, timing and designthe supplier's skill and scale may mean better quality or lower cost than the figures show
no reliance on a supplier who could fail or raise pricefrees capacity, money and management time for the core business
keeps jobs and know-how in the businessflexibility: easy to change supplier or order size
confidentiality for designsno machine lease, no staff to train

Is there spare capacity (section 4)? Is demand steady enough for making to pay?

The decision ties to 5.4: buying is outsourcing, making is insourcing. A judgement states the cheaper option, the figures, the main non-financial factors and a condition that would reverse the choice.