IB Business Management 3.9 · HL only

Budgets (HL only)

How does a business decide what each part of it may earn and spend, and what does it do when the real figures turn out different?

What you will learn

  • HL Know how a cost centre differs from a profit centre and the roles each plays in a business.
  • HL Know how to build a budget in the layout used in IB case studies and exam papers.
  • HL Understand variances and how to label each one favourable or adverse.
  • HL Understand how budgets and variances help managers plan, control and decide, and where they fall short.

You must be able to

  1. HL Calculate the variance on each line of a budget and label it favourable or adverse.
  2. HL Construct a budget from given figures, with totals for revenues, costs and the excess of revenues over costs.
  3. HL Comment on a set of variances, giving the size, a likely cause and an action.
  4. HL Distinguish between a cost centre and a profit centre, with an example of each.
  5. HL Explain the roles of cost and profit centres for a named business.
  6. HL Explain how budgets and variances support decision-making, and one weakness of them.

In the exam. HL Paper 2 has a quantitative focus; its Section A (30 marks) is assessed at AO1, AO2 and AO4 only, and Section B has structured parts and an extended response. Questions are numbers (complete a variance column; prepare budgeted and actual statements) or words (explain why a business uses cost and profit centres, or what budgets and variances are for; comment on results). The guide prints a budget layout (its Figure 11) and says budgets in case studies and exam questions will follow it. The formulae sheet has no budget or variance formula: the working is yours to know.

1Cost centres and profit centres

Both are parts of a business whose figures go to one manager. They differ in what is measured.

Cost centreProfit centre
What is recordedCosts onlyCosts and revenue, so a profit or a loss
The manager answers forKeeping spending within budgetRevenue, costs and the profit that results
Typical examplesHuman resources, IT support, accounts, a central laundry, a research labA shop, a branch, a product line, a region, a division that sells to customers

A business usually has both.

  • Example (invented): Pellam & Cray Furniture Ltd runs three showrooms (Northgate, Eastbank, Hillside). Each sells to customers and its takings are known: a profit centre. The head office and the IT and administration office serve the showrooms but sell nothing to the public: each is a cost centre.
  • The test: can the department's own revenue be identified and measured? If not, it is a cost centre, however important.

The roles they play (give the mechanism, not a list):

  • Control and organisation. One total hides where money goes. With separate centres, a jump in the IT office's software bill traces to one named manager. Seniors step in only when figures slip.
  • Accountability. Each manager answers for the figures of their own centre.
  • Comparison. Pellam & Cray can set the three showrooms side by side and study the weakest. A profitable firm may hide one loss-making branch. Profit centres expose it.
  • Autonomy. A budget holder decides without waiting for head office, so decisions are quicker.
  • Motivation and planning. A target, perhaps with a bonus, gives a manager a reason to perform. The budgets add up to the whole plan.

The weaknesses.

  • Sharing out overheads is a judgement. A profit centre shows a true profit only if it carries a fair share of shared costs. "Fair" is a choice.

The showrooms' results for a quarter results, before any share of the $75k of head office and IT costs ($000):

ShowroomRevenueCosts of the showroomProfit before shared costs
Northgate30025050
Eastbank21018525
Hillside907020
Total60050595
  • Share the $75k by revenue (50%, 35%, 15%). They carry 37.5, 26.25 and 11.25, leaving profits of 12.5, −1.25 and 8.75. Eastbank looks a small loser.
  • Share it equally, 25 each, and the profits are 25, 0 and −5. Now Hillside is the loser.
  • Either way the total is $20k. Nothing in the showrooms changed. Only the rule did.
  • Controllability. A manager can be blamed for what they cannot influence, such as a rent fixed by head office or a supplier's price rise.
  • Pressure and conflict. Managers chasing their own target may compete for resources. They may cut corners (training, safety checks, compliance) to protect their centre's profit at the firm's expense.
  • Cost and time. Recording each centre's figures needs systems and staff.

2Constructing a budget

The guide asks you to construct a budget (AO2, AO4). It prints the layout: a statement of profit or loss with columns for plan, result and gap.

The guide's budget layout (Figure 11)
Revenue: each source, then total revenues
Costs: each cost, then total costs
Excess of revenues over (under) costs: total revenues minus total costs
Columns: budgeted figures, actual figures, variance with [F] or [A]
  • One layout serves profit-making and non-profit organisations, so the last line reads "excess of revenues over (under) costs", not "profit". Some textbooks say "income", "expenses" and "net income".
  • Before the period only the budgeted column is filled in. A cost centre's budget has costs only. A profit centre's has both.

A budget is not a cash flow forecast (3.7). A budget plans revenue and costs when earned and incurred. A cash flow forecast plans when cash moves, and has opening and closing balances, which a budget lacks.

Where the figures come from. Each line is a forecast and needs a reason.

  • Last period's actual figures, adjusted for expected change. This is the usual start.
  • The objectives. A showroom told to grow needs bigger sales and marketing lines.
  • Forecasts of demand, prices, wages and rent.
  • Benchmarking against competitors or other centres.
  • Negotiation between budget holder and finance director. An imposed budget is quick to write and hard to hit.
  • The finance available (3.2).

Worked construction. The Northgate showroom (a profit centre) is budgeting the coming quarter.

  • The same quarter last year sold $240k. A new kitchen range should lift sales by 25%, so budgeted sales are 240 × 1.25 = $300k.
  • Customers who pay for assembly are forecast to bring in $20k.
  • Furniture for resale is planned at 55% of sales: 0.55 × 300 = 165.
  • Staff cost $62k (agreed with the manager), rent $30k (fixed by the lease), utilities $8k, marketing $12k, delivery $14k.
Total revenues = 300 + 20 = 320
Total costs = 165 + 62 + 30 + 8 + 12 + 14 = 291
Excess of revenues over costs = 320 − 291 = 29
  • These fill the budgeted column of the table in section 3 ($000). The excess is 29 ÷ 320 = 9.1% of revenue.
  • A revenue line can use units: 1,500 customers at an average of $200 gives 1,500 × 200 = $300k. When a question says how a line is set, follow it exactly and show every step.

Avoid these errors.

  • Leaving out a cost.
  • Counting a line twice.
  • Taking a percentage of the wrong base (55% of sales, not of total revenues).
  • A forecast with no reason behind it.

Other types. Textbooks name sales, production, staffing, marketing, incremental (last year plus a percentage) and zero-based (every holder justifies spending from nothing) budgets. The guide does not list them. Know the single layout above.

3Variances

A variance = the difference between the actual figure and the budgeted figure on one line.

Explaining variances is variance analysis. The guide prints the labels [F] and [A] but no formula. The convention is:

Variance = actual figure − budgeted figure, shown as an amount with F or A

Then label it with one question: is the gap good for profit, or bad?

LineActual compared with budgetLabel
Revenueactual is higherFavourable [F]
Revenueactual is lowerAdverse [A]
Costactual is lower (spent less)Favourable [F]
Costactual is higher (spent more)Adverse [A]
Excess of revenues over costs, or any profit linehigher / lower[F] / [A]

There is no "positive" or "negative" variance. A higher cost gives a positive number but a bad result. Write the amount and F or A. A variance of zero needs neither.

Worked variances: Northgate. At the end of the quarter the actual figures are entered. The column is worked from top to bottom ($000):

BudgetedActualVariance
Revenue
Sales30028812 [A]
Assembly fees20244 [F]
Total revenues3203128 [A]
Costs
Furniture bought1651605 [F]
Staff62664 [A]
Rent30300
Utilities871 [F]
Marketing12153 [A]
Delivery14173 [A]
Total costs2912954 [A]
Excess of revenues over costs291712 [A]

Working.

  • Sales: 288 − 300 = −12, revenue lower, so 12 [A].
  • Assembly: 24 − 20 = +4, revenue higher, so 4 [F].
  • Furniture: 160 − 165 = −5, a cost lower, so 5 [F].
  • Staff: 66 − 62 = +4, a cost higher, so 4 [A].

Check your table. Each total must equal its lines.

  • Revenue: 12 [A] and 4 [F] net to 8 [A].
  • Costs: 4 + 3 + 3 = 10 [A], less 5 + 1 = 6 [F], nets to 4 [A].
  • The bottom line must equal the revenue and cost variances combined. 8 [A] and 4 [A] both hurt profit, so 12 [A]. If one were favourable, subtract and keep the label of the larger.

Tables with sub-totals. Exam tables often include a gross profit line, with direct costs and overheads split. The same rule applies to every line. A profit line takes F when higher.

Example (invented): the bicycle maker Varrow Cycles ($000):

BudgetedActualVariance
Sales revenue72068436 [A]
Direct materials21019812 [F]
Direct labour1501599 [A]
Gross profit36032733 [A]
Overheads1701766 [A]
Net profit19015139 [A]

Check: gross profit = 684 − 198 − 159 = 327. Its variance is 36 [A] + 9 [A] − 12 [F] = 33 [A]. Net profit 327 − 176 = 151, and 33 [A] + 6 [A] = 39 [A]. The routes must agree.

Preparing from raw data. Given lists of budgeted and actual figures, build each column first, subtotals included. Then subtract.

Cost-centre variances

  • A cost centre has only cost variances.
  • Example: the IT and administration office budgeted $48k (staff 30, software 10, equipment lease 5, travel 3) and spent $52k. Software was 14, the rest as planned. The variance is 52 − 48 = 4 [A], all from software, 40% above its budget.
  • A cost-centre manager looks good by spending less than budget, if the service is still delivered.

Percentage variances. Divide by the budgeted figure (a textbook convention, not in the guide). This shows which gaps matter: marketing 3 ÷ 12 = 25% over; sales 12 ÷ 300 = 4% under.

4Analysing variances

Calculating the table is the AO4 skill. Reading it is the AO2 skill. A good comment gives:

  • the size and direction of the main variances;
  • a likely reason tied to the business;
  • what follows.

Investigating and acting on variances is budgetary control.

Start with the biggest and the surprising. At Northgate the excess of revenues over costs is $12k (41.4%) below budget: 17 against 29. Then:

  1. Sales 12 [A]. The new range may have sold less than hoped, or a rival may have opened. The table cannot say which; say so.
  2. Assembly fees 4 [F]. The service beat the forecast and softened the sales gap, or the forecast was cautious.
  3. Furniture bought 5 [F]. Sales fell, so less stock was needed anyway. Furniture was 55.0% of budgeted sales (165 ÷ 300) and 55.6% of actual sales (160 ÷ 288). No gain in efficiency, a slight loss.
  4. Marketing 3 [A] and delivery 3 [A]. Small in dollars, large in percentages (25% and 21.4%). Marketing rose yet sales fell.
  5. Staff 4 [A]. Overtime, a pay rise, or too many staff for lower sales.

Then suggest action: review the extra marketing, check delivery charges, test the sales forecast.

Questions that sharpen a comment:

  • Controllable or not? A supplier price rise is outside the manager's control. Over-ordering is not.
  • One-off or a trend? One quarter's utilities overspend might be a cold spell. A third in a row is a pattern.
  • Linked to another variance? Costs that move with sales cannot be judged fairly against a budget built for different sales. A flexible budget (textbook idea, not in the guide) restates them for actual sales: 0.55 × 288 = $158.4k of furniture.

Against that, the actual $160k is $1.6k over. The "saving" of 5 [F] was really a small overspend.

  • Was the budget right? An adverse variance may mean a poor plan, not a poor performance.

Causes are internal (waste, absence, quality problems, poor forecasting) or external (competitors, exchange rates, supplier prices, weather, new laws). The cause decides whether to manage better or re-plan.

5The importance of budgets and variances in decision-making

At AO2, explain how budgets and variances feed decisions.

UseHow it helps a decisionAt Pellam & Cray
Planning and setting targetsTurns an objective into figures for each centreGrowing kitchen sales becomes a $300k target for Northgate
CoordinationMakes each centre's plan fit the others and the firm's aimsNorthgate's higher sales target comes with enough delivery budget for the extra orders
Allocating resourcesShows where spending is justified and where it can be cutThe IT office is held to $48k; the fastest-growing showroom gets more marketing
ControlFlags overspending before it becomes a crisisSoftware at 14 against 10 triggers a check of licences
AccountabilityNames who must explain a varianceThe Northgate manager explains marketing and delivery
Motivation and rewardGives a clear target and a basis for a bonusA bonus if a showroom meets its budgeted excess
Judging performance and pricingShows which centres do well and whether prices or costs must changeA cost line that keeps rising prompts a price or supplier review

The weaknesses (these lift an answer above a list).

  • Rigid. A January budget may be out of date by March. Managers may still follow it and turn down a profitable order outside budget. Or they may spend what is left so next year's budget is not cut.
  • Forecasts can be wrong. The plan may be at fault.
  • Padding and gaming. Managers judged on the budget may ask for more than they need. They may understate expected sales so the target is easy to beat.
  • Imposed budgets demotivate. A target handed down feels unfair, above all when the variance is outside the manager's control.
  • Short-term focus. Cutting training, repairs or research to hit this quarter's figure can harm the business later (sustainability).
  • Ethics. Pressure to hit a figure can mean cutting corners on safety or quality, or flattering the figures.
  • Numbers only. Goodwill and morale are not in a budget. Preparing one takes time.
  • Pick two or three that fit the business and connect them.
  • Example: "Because Pellam & Cray's showroom managers are paid a bonus for meeting their budgeted excess, one may postpone staff training to stay on target".
    • That beats "budgets can cause problems".

Practice questions